Sustainable Mobility: Construction of Bucharest 6 Metro Line
Beneficiary: Metrorex
Category: Retaining Wall System
Drilled piles for Lot 1 of the 6 Line project, a significant mobility project for Bucharest. The entire line will have a route of 14.2 km of double track, including 12 stations, on which will operate 12 new, modern trains.
Lot 1 (1 Mai – Tokyo) will cover a length of 6.3 km and will feature 6 stations and 6 interstations.
We completed the retaining wall systems for 4 of the 6 interstations and 2 are under construction, The retaining wall system consists of tangent and secant piles with diameters from 620 to 1000mm and lengths from 10 to 38 m. Works will be completed this year.
This investment will connect Henri Coandă International Airport with Gara de Nord.
The investment objective is part of the Trans-European Transport Network (TEN-T).